1. Sept 2009: Preparatory work commences on site
2. April 2010: Construction begins, the first platform is refurbished and the new concourse is created in the old NCP car park
3. Work to clad the station in its reflective steel facade begins
4. Phase 1 completes. The new station concourse opens for passengers and work switches to transform the existing station concourse
5. 2015: Phase 2 completes and the station fully opens